Project Name: Scrubs Lane & Du Cane Road

 
Project Reference Number: IMGA252149
Project Network: Cadent

Scheme background: Cadent – To replace circa 335.44m of existing 12" Di/Ci main with new 250mm Pe.

TFL - Decommissioning of permanent signals. Deployment of welfare unit. Removal of existing poles and refurbishment of chambers. Installation of new controller base. Installation of signal poles and associated equipment. Commissioning of new signals, removal of temporary signals and welfare unit. Installation signal poles and associated equipment. Commissioning of new signals, removal of temporary signals and welfare unit.

Collaboration Partner(s):
TFL
Project Start Date:
13 October 2025
Length of Collaboration (Meters):
335.44m
Estimated Days Saved:
37
 
Local Authority:
London Borough of Hammersmith & Fulham
Project End Date:
16 December 2025
Level of Collaboration:
Level 2
Project Status:
Complete