Project Name: Rye Lane

  
Project Reference Number: SOE14181
Project Network: SGN

Scheme background: The project was a collaborative effort involving SGN, Forefront Utilities, Thames Water, Morrison Water

Services and Southwark Council, working within the London Borough of Southwark. Although SGN led the
works, the scheme required continuous coordination between multiple stakeholders to ensure smooth delivery.
In addition to scheduled conference calls, supplementary meetings were held between Thames Water and
SGN to maintain momentum. These meetings focused on defining roles and responsibilities, including costsharing
agreements, traffic management (TM) plans.

The works commenced on 14th May 2025 and took approximately 39 days to complete. SGN began on Rye
Lane. SGN worked together with Thames Water and shared Traffic Management so they could install a mains
and service connection.

The scope of SGN’s works included the installation of 70 metres of new polyethylene 630 mm (PE) gas main
and the abandonment of 70 metres of 30” Cast Iron redundant metallic main.

Throughout the project, effective communication was vital. Key stakeholders included, but were not limited to:

  • Greater London Authority (GLA)
  • Thames Water
  • Morrison Water Services
  • Southwark Council
  • Forefront Utilities
  • SGN
  • Transport for London (TfL) Buses
  • Local Businesses
Collaboration Partner(s):
SGN and Thames Water
Project Start Date:
14 May 2025
Length of Collaboration (Meters):
70m
Estimated Days Saved:
21
 
Local Authority:
Southwark
Project End Date:
23 June 2025
Level of Collaboration:
Level 2
Project Status:
Complete