Project Name: Deptford Church Street
Scheme background: The SGN/JDT mains replacement works formed part of Lewisham Council’s regeneration programme, which focused on upgrading roads, footways, and sustainable drainage systems (SuDS) across the borough. The project was located within the London Borough of Lewisham.
Throughout the scheme, regular conference calls were held with JDT, Lewisham Council, Conway, and SGN,
alongside additional coordination meetings. These ensured clear communication of roles and responsibilities
and maintained programme momentum.
The scheme was highlighted during Lewisham Council’s resurfacing and SuDS programme. SGN took the
opportunity to deliver essential gas main and service replacement works in parallel, minimising disruption to the
local community. To facilitate the works, SGN collaborated closely with Conway Traffic Management, who were
already engaged in the council’s wider regeneration programme.
Project Timeline
Conway start date: 25 November 2024 (works ongoing beyond SGN completion)
SGN/JDT collaboration periods:
29 March 2025 – 10 April 2025
23 July 2025 – 1 August 2025
Scope of Works (SGN/JDT)
Installation of 59.5m of 75mm PE main (via a combination of live and dead insertion techniques).
Abandonment of 91.5m of 4” CI main.
All service and connection excavations carried out using vacuum excavation (vac ex) for safety and efficiency.
Temporary backfilling and reinstatement completed by SGN to allow Conway to proceed with resurfacing
activities.
Stakeholder Engagement
The project required close coordination across multiple organisations to remain on programme and align with
the council’s regeneration works. Key stakeholders included:
- Greater London Authority (GLA)
- SGN
- JDT Utilities
- Conway
- Lewisham Council
- Local businesses